Article
Publication date: 8 April 2024

Hasith Chathuranga Victar and Anuradha Samarajeewa Waidyasekara

Construction and Demolition (C&D) Waste Management (WM) poses significant challenges in Sri Lanka, contributing to environmental degradation and resource depletion. To address…

Abstract

Purpose

Construction and Demolition (C&D) Waste Management (WM) poses significant challenges in Sri Lanka, contributing to environmental degradation and resource depletion. To address these issues, this study explores the application of Circular Economy (CE) strategies in minimising waste generation and optimising resource utilisation in Sri Lankan construction industry. The research focuses on the construction and building renovation and use and operate stages of the building project life cycle, recognising their significance in waste generation and resource consumption.

Design/methodology/approach

The research employed a qualitative approach, utilising the Delphi technique through three rounds of expert interviews. Seventeen experts were involved in the first round, followed by fifteen in the second round, and twelve in the final round. The collected data was analysed using manual content analysis methods.

Findings

The research findings revealed fifteen C&D WM issues in the construction and building renovation stage in Sri Lanka, along with suitable strategies to overcome each of them. Similarly, eight C&D WM issues were identified for the use and operate stage of the building, and corresponding strategies were provided to address each issue. By adopting CE strategies such as modular design and material reuse, construction projects can optimise the project's timeline, cost, and quality factors. These strategies enable efficient resource allocation, reduce waste generation, and contribute to the overall sustainability of the project. The impact of CE strategies on mitigating these issues within the project management iron triangle was also discussed.

Originality/value

This paper entails delving into how construction, building renovation, and operation stages of a building's life cycle intersect with CE strategies, which profoundly influence operational efficiency and long-term sustainability. By incorporating principles such as energy efficiency, water conservation, and circular product design, the paper illuminates how these strategies facilitate decreased energy usage, enhanced resource management, and diminished waste production throughout the building's lifespan.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 8 April 2024

Malik Lakshan Hasantha, Anuradha Samarajeewa Waidyasekara and Hasith Chathuranga Victar

Insufficient time allocation for the bidding period occurs, causing drawbacks to both parties, the client and the bidder. Hence, this study aims to evaluate the time allocated for…

Abstract

Purpose

Insufficient time allocation for the bidding period occurs, causing drawbacks to both parties, the client and the bidder. Hence, this study aims to evaluate the time allocated for preparing a bid proposal as per the National Competitive Bidding (NCB) in the Sri Lankan context.

Design/methodology/approach

The study has adopted a mixed method approach and expert interviews and document review to detect, analyse and validate the issues, and solutions based on NCB along with the adequacy of the allocated bidding period used as main data collection tools. Both qualitative and quantitative data were analysed through manual content analysis and inferential analysis respectively.

Findings

Overall, 24 local issues with the existing competitive bidding process and solutions for each were identified. Among the 24 local issues, it was unanimously agreed by all interviewees that three specific issues require attention and improvement. These issues are related to the standard and incompleteness of bidding documents, inaccurate BOQ quantities measured by the consultant or the main contractor, and the excessive number of bidding document amendments by the consultant. It was revealed that a maximum of 42 calendar days (6 weeks) is sufficient for the bidding process while a minimum of 21 calendar days (3 weeks) is insufficient.

Originality/value

The findings of this study would be recommended that Information and Communication Technology Agency (ICTA) understand the necessity of revising the NCB reference to the time allocated for the preparation of bids. By recognising the importance of sufficient time allocation for bid preparation, this research serves as a practical guide for authorities involved in policy formulation, aiding them in implementing revisions that align with the dynamic requirements of bidding procedures.

Details

Engineering, Construction and Architectural Management, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 22 March 2024

Ramgy Pararajasingam, Anuradha Samarajeewa Waidyasekara and Hasith Chathuranga Victar

Construction material management plays a significant role in achieving successful project delivery of a construction project. However, ineffective material management is a…

Abstract

Purpose

Construction material management plays a significant role in achieving successful project delivery of a construction project. However, ineffective material management is a critical issue in the construction industry, especially in developing economies, of which Sri Lanka is not an exception. Therefore, this study aims to focus on exploring the causes of ineffective material management practices in civil engineering construction projects in Sri Lanka and their impact on successful project delivery.

Design/methodology/approach

Furthermore, the literature findings were validated through the preliminary survey. Subsequently, a quantitative research approach was adopted to pursue the research aim. Questionnaire responses were obtained from 215 construction professionals in civil engineering projects who were selected using the judgemental and snowball sampling techniques. Collected data were analysed through Statistical Package for the Social Sciences (SPSS) V26 and Microsoft Excel 2016.

Findings

Moreover, the study revealed that material price fluctuation, shortage of material in the market, delay in material procurement, inadequate planning and delays in material delivery are the most frequent causes of ineffective material management in civil engineering projects. In addition, it was evidenced that most ineffective material management practices cause both time and cost overruns in civil engineering construction projects. Most respondents emphasized inadequate planning, inadequate qualified and experienced staff, lack of supervision and lack of leadership as the causes for both time and cost overruns.

Originality/value

The study was concluded by proposing strategies for effective material management. Education/training/enlightenment of staff in charge of materials management, use of software like Microsoft Project, Primavera and similar software to eliminate manual errors in material management, and providing clear specifications to suppliers were the most agreed strategies for effective material management in civil engineering construction projects.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 13 November 2023

Thisara Manupriya Sathkumara, Anuradha Samarajeewa Waidyasekara and Hasith Chathuranga Victar

The use of renewable energy has become necessary because of the harmful effects of current energy sources on the environment, limited availability and financial crisis…

Abstract

Purpose

The use of renewable energy has become necessary because of the harmful effects of current energy sources on the environment, limited availability and financial crisis. Transparent solar panels have emerged as a promising technology for integrating renewable energy generation into building structures. Therefore, this paper aims to explore the feasibility of transparent solar panels for high-rise building façades in Sri Lanka.

Design/methodology/approach

The research apprehended a qualitative approach, including two expert interview rounds adhering to the Delphi technique with 17 and 15 experts each per round. Manual content analysis was incorporated to analyse the collected data.

Findings

Regarding operation and maintenance, the study emphasizes the importance of regular inspection, cleaning and repair of transparent solar panels to ensure optimal performance and longevity. These activities contribute to maximizing energy generation and maintaining the aesthetic appeal of the building. The benefits of implementing transparent solar panels on building façades are manifold. They include renewable energy generation, reduced greenhouse gas emissions, improved energy efficiency and enhanced architectural aesthetics. Furthermore, the research findings underscore the potential of transparent solar panels to contribute to Sri Lanka’s sustainable development goals and address the country’s increasing energy demand. However, the study also identifies challenges that need to be addressed for successful implementation.

Originality/value

This study contributes to understanding the feasibility of transparent solar panels for high-rise building façades in Sri Lanka. The research findings offer valuable insights into the operation and maintenance aspects, benefits, challenges and strategies for implementing transparent solar panels effectively. This knowledge can guide policymakers, architects and developers in making informed decisions regarding the integration of transparent solar panels, thereby promoting sustainable and energy-efficient building practices in Sri Lanka.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 26 July 2021

Sandunika Sasuli Chiranthi Ginthotavidana and Kapugama Geeganage Anuradha Samarajeewa Waidyasekara

The purpose of this study is to develop a customised model to measure the performance of housekeeping (HK) services in Sri Lankan health-care facilities.

Abstract

Purpose

The purpose of this study is to develop a customised model to measure the performance of housekeeping (HK) services in Sri Lankan health-care facilities.

Design/methodology/approach

An exploratory sequential mixed approach was adopted in the study to collect and analyse data. A case study strategy was adopted in the initial phase to explore the current HK practices, and to determine the applicable key performance indicators (KPIs) found through literature. Semi-structured interviews were used as the data collection method in the selected case studies. A questionnaire survey was conducted in the next phase to verify the validity of case study findings. Quantitative data were analysed using descriptive statistics. One sample t-test was used to identify significant KPIs and to formulate the customised performance measurement (PM) model.

Findings

The study identified and ranked 46 KPIs, which can be used to measure the performance of HK divisions of health-care facilities, in balanced scorecard perspectives. The findings also revealed that the KPIs determined using the model have a significant impact on implementing effective health-care HK services and could be used to measure both real and subjective cleanliness.

Practical implications

The developed model can be used for numerous PM requirements in health-care setups in both developing and developed countries. The KPIs determined using this model can be presented in quality audits and government inspections as proof of effective HK management. The HK managers of the health-care sector can effectively monitor the performance of their divisions using the proposed PM model and this model can be customised to match the other facilities management service divisions.

Originality/value

Many studies focus on overall health-care PM. This study expands the knowledge on HK PM in the health-care sector by presenting a collection of performance indicators centred on HK function.